Services Provided as Primary Subcontractor:
Removed and replaced existing cast iron watermain and install 235 meters of new PVC
Installed 6 new 1200 MHs
Removed and replaced 63.0 metres SANI and STM lines by open cut
Installed 52.7m of SANI and STM CIPP (CURED IN PLACE PIPE) Lining
Installed 2 new water meter chambers
Challenges and Resolutions:
Primary contact with client engineer to provide design advice for major onsite issues including new location of
storm and sanitary lines and maintenance holes.
Severely old infrastructure led to a number of breaks. We lead the way to ensure all problems were resolved in a timely and cost-effective manner to ensure completion of phase 1 of the infrastructure upgrades was completed on schedule.